COMP8770 ASSIGNMENT

PAGE 1 SEMESTER 1, 2021








F A C U L T Y O F SCIENCE A N D E NGINEE RING
D E P A R T M E N T O F C O M P U T I N G

COMP 8770 : IS PR OJ EC T AN D RI SK
MAN AGE M E N T



INDIVIDUAL ASSIGNMENT
NUMBER ONE(1)

“MS PROJECT AND CASE STUDY”
SEMESTER 1, 2021






















Convenor : Dr. Stephen Smith

COMP8770 ASSIGNMENT

PAGE 2 SEMESTER 1, 2021


INDIVIDUAL ASSIGNMENT

DUE DATE: 4:00 pm, Week 4, 15/3/2021
CONTRIBUTION: 20% of Final Mark
DELIVERABLES: MS Project File and Report with Parts A & B
(Submit separately through the iLearn tools)
PART A MS PROJECT BASIC PROFICIENCY
(10 MARKS)
SOFTWARE
Macquarie University and Microsoft have formed an MSDN-Academic Alliance,
allowing MIT students to obtain free copies of MS software. For this course
you will need Microsoft Office Project Professional 2016 or 2019.

Obtain a free copy of Microsoft Office Project 2016 or 2019 using the
following procedure:

Go to the Microsoft Azure Dev Tools for Teaching:

https://azureforeducation.microsoft.com/devtools

Sign in with your Macquarie Uni credentials and then Get Software>View All

You should be able to find Project Professional 2019, as well as Visio
Professional 2019 (which was used in COMP8760).

Your Macquarie portal username and password should work on this site.

If you have any problems with passwords please email Macquarie One Help
http://mq.edu.au/onehelp/
Login to the site and select the applications. Make sure you print (or save)
a copy of the Product key (this is used to activate the program).
Refer to Appendix 2 – for a snip of my screen. Note the location of MS
Project (2nd from the bottom). Plus, note the Product Key on the right.

Currently, the software downloads to your computer as a “.zip” file (this may
take up to a few hours). Go to the location of the downloaded file (see figure
1 below as a sample) then extract the such as WinRAR or 7 Zip. The result
should look like figure 1. Click on the setup.exe and run the program.


Figure 1 – Download view pf Project .zip files

COMP8770 ASSIGNMENT

PAGE 3 SEMESTER 1, 2021


When you attempt to “Activate” the product you may have to navigate away
from the login window (I think it says “login using another user”) to find the
place where you enter the product key (saved beforehand).

If you have any difficulties, download the free 60 day trial version from the
Web and then use your key to upgrade to a fully paid version.
(http://www.mpug.com/resources/microsoft-project-free-trials/ )

For MAC users, there is no native MS Project version. You can install
Bootcamp or a Virtual Machine to emulate Windows, or use the software in
the lab. The postgrad lab is in Room G500 in the EMC Building, please note
this may change this semester with new labs in 4 Research Park Drive. You
can gain access by asking the receptionist in the foyer, or talking to security
after hours.

Please note that this is an INDIVIDUAL ASSIGNMENT. I will be
comparing submitted MS Project files for similarities. As well, I will
be very suspicious of students who make the identical mistakes. If
you engage in a collaborative effort, there is a high probability that
you will be caught and this type of cheating could result in failure of
the whole unit, not just a zero in this assessment item.


COMP8770 ASSIGNMENT

PAGE 4 SEMESTER 1, 2021



ASSIGNMENT BACKGROUND

ABC Development Company has won a contract to design, build and
implement an information system for a large Australian company. The Project
Manager has two types of resources, Programmers and Designers, to be used
in this project. The following table lists the project tasks, their duration in
weeks, precedence relationships, durations and resource requirements.

Task Duration
(Weeks)
Predecessors Programmers
(People)
Designers
(People)
1 1 3 3
2 3 1 1 1
3 4 1 2 0
4 2 1 0 1
5 2 1 2 1
6 3 2 1 1
7 7 3,6 0 2
8 2 4 1 0
9 4 5 1 0
10 6 5 0 1
11 2 7,8 2 0
12 1 9 1 1
13 3 10 1 2
14 2 11,8 2 0
15 3 12 0 1
16 4 13 1 1
17 3 14 0 2
18 4 16 2 0
19 4 15,18 1 1
20 2 17,19 1 1

• Project start date is determined as Monday, April 5, 2021
• Schedule the project from the project start date
• Select the standard calendar template of 8 hours/day, 40 hours/week
and 20 days/month
• Do not worry about public holidays, assume that everyone works as
usual (it’s the new workplace enterprise agreement!)
• There are 8 units (people) of Programmers (P) and 7 units of Designers
(D) available
• P cost $100/hour and D cost $140/hour
• Precedence linking dependent tasks is the usual finish-to-start
• All activities are of fixed duration and to be scheduled as soon as
practicable. Do not split tasks to reduce resources.


COMP8770 ASSIGNMENT

PAGE 5 SEMESTER 1, 2021



YOUR CHALLENGE

1. Submit your MS Project 2019 file using your student number as the file
name through the iLearn (class web site) assignment submission tool.
See the class web site at:
https://ilearn.mq.edu.au/
2. Submit your report, answers to the questions below (AND PART B), as
a single pdf file. Make sure that you include your name and student
number on the front page. Again, use your student number as the file
name.
3. Late submissions will attract the usual 10% penalty per day. iLearn
time stamps all the submissions. You can submit multiple times up to
the deadline without penalty.

Answer the following questions in your report:

1. Provide a table outlining how you allocated the Resources (P1 to P8
and D1 to D7) across the Tasks. What is the minimum number of each
resource necessary to ensure that the project is not delayed due to
over allocation of resources?
2. From the Network Diagram, note the critical path in red, and list the
tasks in order on the critical path. Include a copy of the Network
Diagram in your report.
3. What is the finish date for the project?
4. Use the Tracking Gantt Chart to investigate the non-critical activities.
The Tracking Gantt groups them and shows the slack time as a blue
line at the end of a dependent series. List each of these activities that
have a slack time, and indicate the slack time. This is the Free Slack
Time. We are not interested in the Total Slack which attributes
downstream slack to upstream tasks and can be very deceptive.
5. How much money is spent for each of the activities 1, 5, 8, 12 and 19?
6. What is the total project expenditure?
7. What are the cash flows for each of the one week starting on April 26
and July 5, 2021?
8. a) What are the peak usages of each of P and D, and
b) In which weeks do these peaks occur? We want to know the
maximum resources needed for each of P and D, and the exact weeks
for each peak usage so that it can be correctly scheduled.

COMP8770 ASSIGNMENT

PAGE 6 SEMESTER 1, 2021


Marking Criteria for Part A

• All 8 questions answered correctly: 10/10
• Every error results in the loss of 1 mark; a very minor error will attract a
penalty of 0.5 marks
• A pass mark of 5/10 can be awarded if the student has lost more than 5
marks but the reason is due to the cascading effect of one error
causing a lot more errors e.g. an incorrect task sequence in the Gantt
chart

PART B RISK MANAGEMENT (10 MARKS)

1. (Australian) Vaccine role out !!!

The Prime Minister of Australia Scott Morrison has announced that covid19 vaccinations will begin in early
March 2021 and completed by 31st October 2021.


2. Imagine you are the project manager, you are to create a project plan
based on current information that is feasible and covers real-life
situations
3. Also, you are doing a risk analysis. Construct a table with at least SIX
(6) significant risks. Use the column headings as follows:

a. (Business/Clinical etc) Function(s)
b. Risk Issue (s)
c. Consequence(s)
d. Likelihood(s)
e. Risk Treatment(s) (6 marks)


4. Write a few paragraphs describing the limitations of using MS Project to
create a baseline project plan for this project. What advice do you have
as a Project Manager in how to use MS Project2019 to manage this
project?
(4 marks)

Note – this task is real, I don’t want textbook style answers I want you to
think and provide believable answers.

Add your Part B answers to the report prepared to answer the questions
in Part A.


COMP8770 ASSIGNMENT

PAGE 7 SEMESTER 1, 2021





Marking Criteria for Part B


Element Excellent to Good
(80- 100)
Pass
(50 – 80)
Incomplete
(0 – 50)
Demonstrates
understanding or
interpretation of
key concepts of
risk
management
and MS Project
 Demonstrates high
level of understanding
of key concepts
 Skilfully organises
description of issues
and application of
functions
 Provides an insightful
analysis
 Provides a logical
and complete report
 Demonstrates some
understanding of key
concepts
 Organises description
of issues and
application of functions
in some cases
 Provides a reasonable
analysis
 Provides a mostly
complete report.
 Demonstrates little
understanding of key
concepts
 Little organisation used to
describe issues; shows
poor application of
functions
 Includes an incomplete
analysis
 Provides an incomplete
report.